5. Connect to the data logger. Connect the ends of the sensor cables to the appropriate
terminals as shown in the wiring diagram that comes with the data collection program
(Appendix A.6. Wiring diagrams). REMOVE THE RED CAP AFTER INSTALLING
THE PYRANOMETER (save for future storage/shipping). If the red cap is not removed
no data will be collected.
Figure 16: Diagram showing the mounting configuration for the LI200X pyranometer using a CM225 stand
(adapted from Campbell 2008).
3.17 Rain Gauge (TB4MM-L)
Equipment/supplies needed:
Plastic cable ties
½” PVC pipe
Wire cutter/stripper
Allen wrench
4.8x100-110 cm steel pipe
Precipitation sensor (TB4)
Wind Shield (Novalynx 260-953)
Manual precipitation gauge
The rain gauge should be installed at least 6 m away from the climate tower (following the siting
instructions given in Sections 2.6, 2.7 and 2.8) and 30-40 cm above the ground on a leveling base
on top of a pole. Visual instructions for installing the rain gauge can be watched on the TEAM
portal in the Climate Protocol section in the “Installing the precipitation bucket” video
(http://www.teamnetwork.org/en/protocols/threat/climate).
1. Installing the mounting pole. There are several commercial options available for poles
but a simple and cheap solution is to buy a steel pipe 4.8 cm wide and 100-110 cm long
driven into a concrete foundation in the ground 70 cm deep by following these directions:
a) Dig a hole 70 cm deep by 15-20 cm wide.