SP Lite2 Silicon Pyranometer
1. Attach the mounting arm to the tripod or tower at the required height.
2. Loosely attach the SP Lite2 to the mounting arm using the two bolts (M5
x 40), washers and nuts. Mounting screws are provided with the SP Lite2.
3. Thread the three M5 x 25 leveling bolts into the base of the SP Lite2.
Adjust the three leveling bolts as required to center the bubble in the level.
Tighten the two mounting bolts.
4. Wiring
The SP Lite2 can be measured with a differential or single-ended channel on
the datalogger; a differential channel is recommended and does require a user
supplied jumper between the signal reference wire and a ground terminal.
Please review Tables 1 & 2 for sensor wiring.
TABLE 1. Datalogger Connections for Differential Measurement
Function Colour
CR800, CR1000,
CR3000
CR10X, CR510 CR23X 21X/CR7
Radiation Signal Red Differential H Differential H Differential H Differential H
Signal Reference Blue Differential L Differential L Differential L Differential L
Jumper to
AG
Shield Black G G
TABLE 2. Datalogger Connections for Single-Ended Measurement
Function Colour
CR800, CR1000,
CR3000
CR10X, CR510 CR23X 21X/CR7
Radiation Signal Red S.E. Channel S.E. Channel S.E. Channel S.E. Channel
Signal Reference Blue
AG
Shield Black G G
5. Datalogger Programming
The SP Lite2 outputs a low-level voltage ranging from 0 to a maximum of
about 120mV. A differential voltage measurement (VoltDiff, or Instruction 2)
is recommended because it has better noise rejection than a single-ended
measurement. If a differential channel is not available, a single-ended
measurement (VoltSE, or Instruction 1) can be used. The acceptability of a
single-ended measurement can be determined by simply comparing the results
of single-ended and differential measurements made under the same
conditions.
7